CH-02: RESPONSIBILITIES:
The following responsibilities outline the important activities that should be accomplished to satisfy the scope of the Work Permit System.
2.1 Responsibilities of Permit Issuer:
Below are certain responsibilities of permit issuer for guidelines but are not limited
- Concerned plant shift engineer or shift supervisor will make a joint site visit with permit receiver. The purpose of this visit is to carry out job discussion & identify the potential hazards.
- Permit issuer will ensure that conditions are safe to work before issuing the work permit.
- Permit issuer will then prepare the equipment to be worked on and properly tick the checklist items.
- Permit issuer will then identify & indicate any potential hazards.
- He/She will advise on protective measures & mention special instructions where required.
- Arrange to carry out gas test wherever required and record the result on work permit.
- Discuss & explain with receiver about the potential hazards that may be encountered during job execution.
- Carry out complete isolation (Electrical / Mechanical / Process) whenever required. Also ensure the isolation through LOTOTO, opening drains etc.
- Follow the LOTOTO protocol where required.
- Area owner will ensure the proper housekeeping of the work place before the job to address the housekeeping issues (oil spillage, housekeeping, insulation etc.)
- Housekeeping is the responsibility of job executor after the job is complete or end of permit duration.
- Close the permit when the job is complete or end of permit duration, whichever is earlier.
- File and retain the permit record for at least one month.